Today Alderman Colon forwarded us a message from CDOT which included the scheduled work dates of the Home Zone project. According to CDOT, our project is scheduled to run from 7/27 through 8/6.
It looks like work will be completed in two weeks!
NO. PROGRAM WARD APPL # LOCATION BREAK DATE POUR DATE BACKFILL DATE GRIND DATE ASHPHALT PLACEMENT DATE PROJ END DATE 2 MENU BUMP OUT 35 048037 2400 N ALBANY AVE 7/27/2010 7/28/2010 8/2/2010 8/3/2010 8/4/20108/6/2010
Contractors came today to mark our street for construction. They said the construction should start in the couple of weeks!
Today Alderman Rey Colon confirmed that the Home Zone is on the list of projects slated for completion in the 35th ward.
It looks like the project will be happening this Summer!